Summary Notes of the Eight Meeting
of Sub Working Group on the Commissioning of the Machine Protection System,
Wednesday 18th July 2007
Present:
Brennan Goddard, Eva Barbara
Holzer, Ivan Romera, Alejandro Castaneda, Rudiger Schmidt, Jan Uythoven
CC: Ralph Assmann, Roger Bailey, Reyes Alemany
Fernandez, Magali Gruwe, Verena Kain, Mike Lamont, Alick Macpherson, Blanca Perea Solano, Laurette Ponce, Bruno Puccio, Stefano Redaelli, Benjamin
Todd, Jorg Wenninger, Markus
Zerlauth,Walter
Venturini
1. Comments on the minutes
There were no specific comments on
the minutes of the previous meeting.
2. MPS aspect of the
commissioning of LHC Beam Dumping System
Brennan Goddard presented an
overview of the commissioning procedures of the LHC Beam Dumping System (LBDS).
Details of the presentation can be found on the slides and in a draft of the
commissioning procedures which was also presented. Some items were left open
for discussion in a future meeting, due to the limited presence of people
caused by the holiday period.
Some discussion points noted during
the meeting:
- After
injection of the first pilot, it should be checked that this is dumped at
the end of the beam dump line. Before optimisation of the beam dumping
system, optics measurements will first have to be performed on the
circulating beam.
- Checks
to be performed at intermediate energies, should be done on the fly,
without stopping the ramp.
- The
details of how the abort gap monitoring will be used in terms of alarms
and/or interlocks needs to be followed up in the MPWG (follow up R. Schmidt).
- The
positioning of the TCDS and TCDQ are very critical for the general machine
protection. The control HW is designed, built, installed and maintained by
the BT group. In agreement with the collimation project and the MPWG the
system includes an LVDT position sensor which will be used for interlocking
the position. The acquisition of this signal, the generation of the
interlock and the incorporation into the collimator control system is
presently under discussion This should also be followed-up by the MPWG.
- Further
outstanding issues are mentioned on slide 17:
- Mapping
between the general commissioning procedures, full system commissioning
procedures and the general LHC commissioning procedures. How to keep them
coherent in case of changes? This is a general issue which should be
discussed in one of the next meetings.
- How
do we assure that only authorised beam is used? This concerns intensity
(most important), but also energy, filling patterns, emittance, particle
type. This should be discussed in a special meeting within this
working group.
3. AOB
- A
presentation on the MPS Commissioning was given to the LHC Machine
Advisory Committee, see slides. The report by the committee concerning the MPS was positive
and no special remarks or requests for follow-up were made.
- The
WIC procedures have been added to the list of procedures, Ivan is
going to add the tests to be done with a squeezed beam.
- Barbara
told that the BLM procedures should be ready for circulation in the week
of 30th July.
- Good
progress has been made on the procedures of the BIS.
- In
the meeting it was said that the next meeting would be in 6 weeks. However,
due to absences, the next meeting will be on Wednesday 12th September.
The agenda can be found here.
Jan
Uythoven, 20/7/07.