Topics 

Topic

Responsible

Date@LHCCWG

Injection and First turn

Sector test team

08.03.06

Circulating beam, RF capture

GA, AB

22.03.06

450 GeV: initial commissioning

JW, FZ

05.04.06 ?

450 GeV: detailed measurements

FZ, MG, SF

 

450 GeV: 2 beams

RA, JU

 

Nominal cycle

 

 

Snapback – single beam

 

 

Ramp – single beam

 

 

Single beam at physics energy

 

 

Two beams to physics energy

 

 

Physics

 

 

Commission squeeze IR 1 and IR 5

 

 

Physics partially squeezed

 

 

 

 

 

75ns operation

GA, FZ

22.03.06

TI2; commissioning plans

 

 

First turn; tracking between sectors

 

 

Collisions at 450 GeV

 

 

Luminosity monitoring (with LHCf)

 

 

 

 

 

RADMON; commissioning plans

 

 

RAMSES; commissioning plans

 

 

Vacuum; commissioning plans

 

 

FiDeL; commissioning plans

 

 

BLM; commissioning plans

 

 

Cryo; commissioning plans

 

 

Magnetic reproducibility (covered by FiDeL?)

 

 

Squeeze IR 2

 

 

Squeeze IR 8

 

 

Effects of LHCb dipole polarity switch

 

 

Effects of ALICE dipole polarity switch

 

 

 

 

 

 

 

 

topics arisen from meeting discussions 

topic reference LHCCWG
loss distribution of collision debris 22.03.2006
sensitivity of luminosity signal, e.g., to IP orbit angle or pressure. 22.03.2006
simulation of beam signals and tune resolution in LHC 22.03.2006
rephasing between rf systems of the two rings 22.03.2006
energy tracking between sectors 22.03.2006