Phase A.1 |
First turn: injection
commissioning; threading, commissioning beam instrumentation. Ring 1,
ring 2. |
|
Phase A.2 |
Circulating pilot: establish
circulating beam, closed orbit, tunes, RF capture, ... |
|
Phase A.3 |
450 GeV initial
commissioning: system commissioning: instrumentation, beam dump,... |
|
Phase A.4 |
450 GeV optics:
beta beating, dispersion, coupling, non-linear
field quality, aperture,... |
|
Phase A.5 |
450 GeV, increasing
intensity:
prepare the LHC for unsafe beam |
|
Phase A.6 |
450 GeV, two beam
operation |
|
Phase A.7 |
450 GeV,
collisions |
|
Phase A.8 |
Snap-back and ramp:
single beam/two beams |
|
Phase A.9 |
Top energy checks |
|
Phase A.10 |
Top energy, collisions |
|
Phase A.11 |
Squeeze: Commission the betatron squeeze in all IP's |
|
Phase A.12 |
Beam commissioning with
experimental magnets |