Entry condition |
E.A.6.1 |
Operation at pilot intensity up to 3 x 1010 protons: |
E.A.6.1.1 |
Both
beams have
completed
single-beam commissioning
(phases A.1 to A.4) |
E.A.6.1.2 |
Emittance ≤ 3.75 μm |
E.A.6.1.3 |
Lifetime > 5 h |
E.A.6.1.4 |
Orbit and optics adjusted for required n1 in aperture |
E.A.6.1.5 |
Nominal
injection tunes |
E.A.6.1.6 |
Hardware commissioning of
separation bump magnets |
E.A.6.1.7 |
Detector magnets OFF |
E.A.6.1.8 |
Simultaneous
operation of the two RF systems |
E.A.6.1.9 |
Injection bucket monitor/selector
commissioned |
E.A.6.1.10 |
Tagging of 25 ns slots done |
E.A.6.1.11 |
Agreement on where bunch 1 should
collide (e.g. IP1) |
E.A.6.1.12 |
Radial position consistent for both
beams (from phase A.2) |
E.A.6.1.13 |
Separation bump knobs prepared
in LSA (base bump, orthogonal bumps) |
E.A.6.1.14 |
Simultaneous acquisition of beam parameters for both beams
|
E.A.6.2 |
Operation at higher intensities: |
E.A.6.2.1 |
Phase A.5 completed for both beams |
E.A.6.2.3 |
Strategy for filling both rings
established (interleaved,...) |