Entry Conditions for phase A.5:

 

Finished phase A1 - A4 successfully.

Particularly important procedures from the previous phases:

  • Mechanical aperture of the machine known in number of sigma

  • fine timing adjustments of dump system with 2 pilots beam (phase A.3.9.2.3)

  • TDI at roughly 10 σ (Phase A.3.4.1.1) to prevent D1 from quench (no beam based alignment, coarse setting)

  • orbit feedback working in injection region, dump region and collimation areas

  • transverse damper working to avoid injection oscillation (check done in phase A.3)

  • abort gap watchdog commissioned

Other entry conditions:

  • complete hardware commissioning of LHC BIS finished successfully, including all interfaces

  • Hardware commissioning tests of vacuum, QPS, PIC, WIC passed successfully (see procedures defined within the MPSCWG)

  • critical settings ready in the database and functionality tested

  • transfer lines TI 2 and TI 8 commissioned with intermediate (2 1012 p+= 1/4 of the nominal injection) beam intensities

  • Injection BIS completely hardware commissioned and commissioned with beam up to TI 8 downstream TED

  • Injection BIS in injection region commissioned without beam

  • No unmaskable interlocks disconnected.

  • Orbit feedback working

Beam requirements

  • Beam 1 and Beam 2 separately, easy change from one to the other.
  • single pilot or intermediate bunch, 43 bunches (filling scheme [5]) and 156 bunches (filling scheme [6])

  • Nominal and reproducible beam emittance of the circulating beam (value agreed for ramping) for previous intensity

  • Reproducible emittance from injector chain