|
Entry condition |
E.A.12.1 |
Beam 1 and beam 2 commissioned at 450 GeV,
with the "setup" intensity |
.01 |
Injection of beam 1 or beam 2 on request. |
|
2 beams circulating with a good life
time. |
.03 |
Orbit measured, corrected and
optimized. |
.04 |
Tune measured and corrected. |
.05 |
Chromaticity measured and
corrected. |
.06 |
Machine coupling measured and
corrected. |
.07 |
No crossing angle, no separation bump. |
.08 |
1 bunch per beam, the beams are
separated longitudinally. |
E.A.12.2 |
Ramp commissioned,
stable beam at 7 TeV (also at setup intensity) |
.01 |
2 circulating beams accelerated to 7 TeV. |
.02 |
Beams at 7 TeV with a good lifetime,
tunes and coupling measured and corrected for both beams. |
E.A.12.2 |
Instrumentation. |
.01 |
Tune measurement systems fully
operational and tested. |
.02 |
Coupling measurement procedure commissioned (closest tune approach
or other techniques). |
.03 |
Orbit measurement fully operational and
tested. |
.04 |
Beam losses monitor system fully operational and
tested. |
E.A.12.3 |
Parameters, knobs. |
.01 |
A
coupling knob per beam is defined and has been tested. |
.02 |
For Alice and LHCb, a knob is
defined to change the internal crossing angle from 0 to +/- nominal |
E.A.12.4 |
Atlas Toroids
have been switched On and tested already. |
E.A.12.5 |
The experiment
magnets (solenoids, compensators and spectrometers) have been
commissioned without beam from the CCC (During hardware
commissioning phase) |
E.A.12.6 |
All
experimental solenoids and dipoles (including the dipole
compensators) are OFF. |