Phase A.12: Beam Commissioning with Experimental Magnets

 

 

Description:

 

Summary of the experimental magnets and their effect on Beam (c/o ML - main reference W.Herr's : The effect of solenoids and dipole magnets of LHC experiment [1])

 

  Description Coupling Orbit Commissioning conclusion
ATLAS solenoid Magnet length ~ 5.3 m. Max. field 2T.
Integrated field ~ 12 T.m
Max. radial field 5 e-4 T
Negligible Can be neglected (1 microrad from crossing angle at 450 GeV) Bring on and leave on after prefunctory checks at 450 GeV
ATLAS toroid No effect on beam     As required by Atlas.
         
ALICE solenoid Central field 0.5 T
Max Radial field 20 e-4 T
Magnet Length ~ 12 m.
"The maximum field is ~ 0.5 T and it can be neglected." Orbit kick from crossing angle at 450 GeV about 1 microrad - neglectable.

Need radial field distribution to be sure but integrated field strength likely to be negligible. (12 m x 20 Gauss gives 16 microrad at 450 GeV).

Bring on and leave on after prefunctory checks at 450 GeV. Don't worry about polarity changes.
ALICE dipole spectrometer
 
field direction H
kick V
B.dl ~ 3 T.m
~ 130 microrad at 7 TeV
-
Strong orbit distortion around the machine.
Compensation  provided by 3 dedicated magnets -> closed, antisymmetric bump
Dedicated commissioning at 450 GeV and in ramp.
         
CMS solenoid Magnetic length ~ 13.2 m
Max. field 4 T ("significantly stronger that ATLAS")
Integrated field ~ 52 Tm
Radial field ~ 20 e-4 T at 1 mm from axis
At 450 GeV:
delta cminus ~ -5i e-3 compared with tolerance of 0.03. Contribution relevant when solenoid is at full field at injection.
With crossing angle on - vertical kick of ~ 5 microrad

Integrated Bdl from radial field - negligible

Measure and correct coupling at 450 GeV. Turn off for first ramp attempts - want to minimise effect of coupling on tune measurement. Check orbit when we bring on crossing angles.
         
LHCb dipole
spectrometer

 
field direction V
kick H B.dl ~ 4.2 T.m ~ 180 microrad at 7 TeV
-
Strong orbit distortion around the machine.
Compensation  provided by 3 dedicated magnets -> closed, antisymmetric bump
Dedicated commissioning at 450 GeV and in ramp. Have to repeat for operation with crossing angle and on change of polarity.

 

The procedure is split in 2 parts :
    Commissioning of beam with the solenoids ON:
            The solenoids have to be ramped to full current at 450Gev and their effects on the beam coupling and the beam orbit have to be measured and corrected.
    Commissioning of beam with the dipoles ON:
            The dipoles and the dedicated compensators have to be switched ON, and gradually put to their nominal strength. The bump closure and induced beam losses have to be measured and corrected before increasing the bump amplitude.