Summary notes of the
forty-seventh meeting of the LHC Commissioning Working Group
Tuesday June 10th, 14:00
CCC conference room 874/1-011
Persons
present
Minutes of the Previous Meeting and Matters
Arising
Roger explained that several LHCCWG
members were absent due to other parallel events, in particular an audit of the
BLM system. There was one comment on the minutes of the 46th
meeting, received prior to this 47th meeting. Namely on the issue of
transfer function and magnetic model Luca Bottura had
clarified by email that his team was including all known and measured effects
in the transfer function models they were providing. Luca was also compiling a
table of estimated modeling accuracy, which Rob Wolf would present at an
upcoming LTC. Luca’s team had discussed with Mike and Marek
the use of the integral transfer function and magnetic length, and the present
mechanism was designed consistently, i.e. it “should” provide the expected
correspondence to the MAD optics. Intensive testing of these models was
recommended nevertheless. Jorg remarked that he had obtained the same answer from Walter,
namely that all data were renormalized to the magnet length listed in MAD.
LHC
Status (Roger)
Roger announced that this was the
first time that the whole machine was either cold at 2 K or being cooled down.
The target date for closure of the experiments and caverns had slightly been
shifted, to the end of July.
The powering tests in Sector 78 were
80% complete, the dipoles had been ramped up to 7 kA, and almost everything was
commissioned in this sector except for the triplet. In Sector 56 a dipole
training campaign had been ongoing through the whole of May. There were about
30 quenches in total, and a current of 11.12 kA had been reached. The rate of
current increase was much lower than expected from SM18 data. In the ICC
meeting of the previous Friday, Ezio had reported how
the magnet people were refining their model. The slow progress at high magnet
current was explained by a loss of memory for a fraction of the Noell magnets. Methods to speed up the quench training were
under study.
On Friday, during a regular training
quench and quench propagation to the neighboring dipoles, a “symmetric quench”
had been observed, i.e. the quench was symmetric between the two apertures,
while the magnet current was ramping down, possibly revealing a hole in the
QPS. Oliver pointed out that on the ramp
down not all the quench signals were being looked at.
Continuing his LHC status summary,
Roger reported that the training campaign in Sector 56 had now been stopped,
and that there would be only a limited training campaign in Sector 78. One of
the consequences of the stop of the training effort in 56 was that work on the
beam-dump dilution kickers would happen this week, and should be finished by
its end. Lyn would soon make a decision on other interventions, e.g. on the
water cooling intervention (in a few weeks time), and on cryo-electronics
work in Point 8. Sector 56 would be
available for operation in the following week. Gianluigi
and others would develop a test & study plan this sector.
Gianluigi remarked that one item to study could be the impact of possible
limits on the “current acceleration”, d^2I/dt^2. Stephane
recommended to perform a dry run of the
squeeze including all trim quadrupoles and all sextupoles and thereby also to enhance the sensitivity
to the acceleration limit. He warned that 10 minutes had so far been foreseen
for the squeeze, but with the new limits the time needed might be significantly
longer. The limits were likely to come from the trim magnets and the lattice sextupoles. Alick recommended to reserve independent console space for OP
commissioning.
Roger reported an issue with the
strengths of the triplets in Points 2 and 8. Oliver clarified that this was a
problem of the power converter and not of the magnets: the installed power
converters could not reach the nominal current of these triplets for the
injection optics ramped to 7 TeV. The maximum magnet
strength had been specified as 230 T/m, and a reduced upper value of 200 T/m
limit had been set for high radiation, which is not expected in these two
points. The reason why a field above 200 T/m was needed when ramping the
injection optics to 7 TeV was constraints on the
phase advance between the kicker and TDI at injection. If there turned out to
be a problem with the strength, one could always change the optics before, or
on, the ramp; otherwise it would be varied prior to the squeeze at top energy.
Oliver recalled that this problem had been brought about by the decision to use
the TCLI collimators. Paul clarified that the power converter problem was
related to the DCCT and not to the number of converter modules. Frank remarked
that in any case this was not a problem for the 5 TeV
run. A response was that the optics will be commissioned up to 7 TeV in 2009, and one should try to explore its feasibility
in 2008.
MPS Commissioning (Jorg
)
Jorg explained that the MPS commissioning may be split into
two parts: a technical commissioning
of all interlock systems, and a beam
commissioning where correct settings will be established. He concentrated
on the first part in this presentation.
Answering
to a question by Roger, Jorg confirmed that he had recently been put in charge
of MPS commissioning, at least for the period prior to beam commissioning, and
perhaps for afterwards as well. He underlined that he would need a lot of help
to do this job.
Jorg showed that the BIS comprised two parts: the BIS core and
all connections. For the BIS, a user
connection test was in progress. At the beginning of July the core would be
ready, fully commissioned by Bruno Puccio’s team. From then on, one could hook
up systems and perform independent tests. One major input to the BIS is the powering system (representing more than
50% of all interlocks). One distinguishes between maskable (for safe beam) and
non-maskable interlocks. The powering interlocks themselves comprise sc magnets
(most sub-parts of which are checked during HWC), the powering interlocks for
nc magnets, and the magnet current monitors. PIC tests require that 2 adjacent
sectors be available and reserved for the tests. The powering interlock effort
is driven by Markus Z., Alvaro, et al. Checks must be performed that the
logging is correct, and test results will be documented in MTF. For PIC 4 days in total were needed. Every
day a different pair of sectors could be commissioned. As soon as 7-1 and 8-1
were ready, one could start to commission the first two sectors.
Roger asked
whether the hardware commissioning activities would care about the magnet
current monitors. Jorg replied that the FMCMs were
not yet commissioned.
Jorg continued his tour of MPS commissioning, where the next
item was the WIC – for which the same exercise was performed, going through all
converters. The WIC and FMCM commissioning could be done at the
same time, on the same day for pairs of two sectors. This would make sense as
the same people were involved in both. One should use the sequencer to support
this activity.
The next big component
of the MPS to be commissioned was the vacuum system. Vacuum valves in one
octant can only be opened when proper conditions are fulfilled (magnets cold
etc.) The commissioning of the vacuum system is being followed up by Gianluigi.
Several details were still to be defined, e.g. should everything be checked, or
would random sampling suffice, or should we plan for a mixture (testing
everything in the first sector and taking random samples later)? These
questions were delegated to Gianluigi. The vacuum MPS commissioning would have
to wait until the BIC was ready, i.e. until the end of the BIC reliability
runs. There were 24 connections from the vacuum to the BIC per IR.
Stefano
pointed out that the need to wait with MPS commissioning for the BIC was a
general problem also for other systems. Gianluigi remarked that other items to
be checked for the vacuum were logging, post-mortem, and alarms. He would try
to get the alarms ready for the time of interlock checks.
Alick stated that each of the user systems should be aware of
the consequences of switching a flag to “false”. Jorg cautioned that there were
some inconsistencies and differences between various user systems. Replying to a question, Gianluigi explained that
there was a vacuum-system logging for each change of state of a valve. Roger
commented that this general effort continued the work of Jan and his subWG.
Jorg agreed, adding that in many cases a well defined procedure existed, but
for some cases not or not yet.
The next MPS
item was the collimation system. The collimator interlocks included position
and environmental parameters. Settings and test had been defined and would
start soon. These efforts were driven by the collimation team.
Oliver,
referring to Ralph, asked whether the collimation should be part of the MPS
system or not. Ralph agreed with Jorg’s approach, elaborating that the system
was designed as a cleaning system.
Responding to a question by Frank, Jorg explained that the term
“environmental parameters” alluded to items like the temperature of the jaws.
Ralph commented that an automatic function was developed by Stefano which would
drive the various interlocks, and log the BIC response at the same time.
Next in line
was the beam dump system, for which
tests were ongoing during the dry runs. In the LBDS everything was related to
MPS. A specification for the Integrated Systems Tests (ISTs) was available but
the MPS specifications were almost empty. Another concern was that the beam
energy tracking system (BETS) had a lot of external inputs, and BETS tests
could only be performed when all energy sources were connected.
Jan commented
that one could use the MB signal from one sector, and split it, for partial
commissioning. It might be necessary to do first tests with such a simplified
configuration.
The beam loss monitors are another special
system. Here the IST and MPS tests were basically the same, but the IST
specifications appeared to be in better shape.
Jorg made the proposal to replace the MPS specifications by IST
specifications. He also pointed out an unusual split of check tasks, a point
which he would follow up after the BLM audit was finished. Jan commented that one could perform an
automated test after every fill to test the BLM functionality. However, the
scope of the automatic tests would need to be defined, and a lot of question
marks remained.
Screens and
mirrors came under the heading BTVs.
Their interlocks will be commissioned as soon as the BIC connections were
ready. The commissioning could be facilitated by re-using automated test
software from the SPS transfer lines developed by Jorg, and Rossano
was pursuing this.
Now turning
to the experiments, here several
categories existed: magnets, movable detectors, ‘emergency dump’, and injection
inhibit. Some question marks pertained to the readiness of TOTEM. Alick had
volunteered to follow this up.
Roger asked
whether the “beam emergency dump” was linked to the beam condition monitor. Jorg replied yes.
The injection system comprises vacuum,
BLMs, MKI, FMCM, and collimators. This system was a relatively modest effort,
and partial tests had been done during dry runs already.
Other systems included operator button (Bruno and BIS team), aperture kickers,
injection kickers, beam position in IR6, rf &
transverse feedback (only rf cryo for startup), beam current monitor, and
access system.
Alick posed questions about access safety and the LBDS.
Jorg answered that there was a direct and an indirect link from the LBDS to the
BIC.
Roger
inquired if there was clear definition of what can and can’t be masked. Jorg
replied yes.
Mathias
expressed some surprise that there was no rf
interlock, pointing out that a debunching beam might compromise the machine
safety. Frank remarked that a debunching beam should be detected by the abort
gap monitor. However, Jorg and Rhodri replied that there was no connection from
the abort gap monitor to the BIC at the moment.
Jan
commented that the aperture kicker was maskable, but that it was supposed to be
operated with safe beam only. Jorg
further elaborated that indeed the interlock for the aperture kicker key could
be masked, and that this mask was taken into account only for a safe beam.
Jorg continued his presentation looking at the SIS. The SIS would produce 4 signals:
injection inhibit for beams 1 and 2 communicating with the injection BICs, the
beam dump of both beams connected to the CCR BIC, and some alarms. The plan for
the early commissioning period was to keep the SIS interlocks at alarm level
and to see how they work, before activating them, since there was a lot of
software behind. In particular, the SIS signals were not yet sent to the BICs
to avoid interference with the BIS. Concerning the SIS commissioning, Jorg
recalled that the SIS included the 800 cold orbit correctors which were not
treated in the PIC and which could trigger an injection inhibit. Their
interlock test could be automated with a sequencer. Other groups of items which
are part of the SIS are the BTVs, the integrated fields of the CODs, the
current limits on separation dipoles & MCBX, the RF cryo system, as well as
energy & intensity limits. Jorg naturally was in
charge of the SIS MPS commissioning.
Oliver asked
whether other types of test would also be done, e.g. try to fire an injection
kicker after an injection was complete, that is to do something that should not
be possible and see how the system reacted. Gianluigi remarked that the
injection was immediately inhibited, as soon as one went out of the allowed
energy window. Jorg commented that many similar items were described in the
procedures. Frank asked about the relation of BIS and SIS. Jorg explained that
the SIS was a software input into the BIS. Oliver asked whether one also
verified components protection, e.g. against driving rf cavities through
resonance. Jan replied that the rf frequency was part of beam dumping system.
There also was an RBAC limit preventing certain potentially harmful actions. It
was recalled that the momentum limits imposed by the beam dumping system were
tighter than the ring acceptance. The RF voltage was monitored too. Frank
commented that maybe the cavity tuning could be an issue as it had been in
HERA.
Ralph
remarked that no procedure was prepared for measuring chromaticity or
dispersion, where the collimators would have to follow the off-energy orbit
shifts. Jan or Ralph S. replied that this was not a problem for chromaticity as
one needed to modulate the orbit by microns only, in which case the collimators
would not need to follow the beam motion presumably. Concerning dispersion, it
could be measured by injecting a single bunch and measuring dispersion at
injection.
Summarizing
his presentation, Jorg stressed that the MPS
commissioning would start soon, at the beginning of July, when all BIS
connections as well as major systems (powering, collimation) would be ready.
Some clarifications were still needed for the BLMs and LBDS procedures. The
commissioning of the “safe machine parameters” was yet to be defined by the BIS
team and Alick.
Jan asked
about the documentation of the tests and the demonstrated performance. Jorg
answered that some systems, e.g. powering, would record the test information
automatically in MTF; for others this was not defined. Alick commented that
choosing a method of documentation was left to the user systems, and MTF might
be an option. Roger remarked that this was part of a more general
question. Paul commented that MTF
required EDMS, which was not guaranteed to be always available. Rhodri added
that EDMS, however, was a convenient tool for describing a system state and for
signing off.
Jan pointed
out that if one did not make the documentation effort now, probably one would
never do it. Rhodri stressed that a track record of MPS tests would be
important. Jorg said he would organize discussions on this topic over the next
days.
Next Meeting
Tuesday June 17th,
14:00
CCC conference
room 874/1-011
Provisional
agenda
Minutes of
previous meeting
Matters arising
TOTEM Roman
Pot Operation at the LHC (Ernst Radermacher)
Sector 56 –
preliminary test plan (Gianluigi)
AOB
Reported
by Frank