Summary Notes of the Fifth Meeting of Sub Working Group on the Commissioning of the Machine Protection System,
Wednesday 18th April 2007

 

 

Present: Bernd Dehning, Brennan Goddard, Verena Kain, Laurette Ponce, Bruno Puccio, Stefano Redaelli, Rudiger Schmidt, Benjamin Todd, Jan Uythoven, Markus Zerlauth, Jérémie Fleuret, Juan Blanco, Ivan Romera, Alejandro Castaneda, Robert Harrison

 

CC: Ralph Assmann, Roger Bailey, Eva Barbara Holzer, Mike Lamont, Blanca Perea Solano, Jorg Wenninger

 

 

1. Comments on the minutes

There were no specific comments on the minutes of the previous meeting.

There was a question on the ‘checked by list’ of names for the procedures. It was decided to determine the name on a case by case basis. For the Vacuum System Procedures Gianluigi and Frank should be added to the list. By default all EICs and CICs should be on the list.

In the template there is the indication how often certain tests will need to be repeated. It was asked if there should also be the option “to be repeated after every fill”. This was rejected, as the aim is to follow-up the result of the tests in MTF, and this is not practical to do for every fill. Instead of a commissioning procedure, this then becomes an operational procedure.

2. MPS aspect of the commissioning of the Power Interlock System (PIC)

Alejandro presented a draft version of the commissioning procedures of the Power Interlock System (PIC). He started with an introduction of the layout of the system: the PICs are grouped together in 2 x 8 loops, with each loop being connected to two BIC User Interfaces, giving the required redundancy for all signals connected to the BIC. The essential circuits are unmaskable, the auxiliary circuits are maskable, with the two circuits being on separate loops connected to the BIC. Alejandro reminded the interface to the underlying systems: Power Converters, Quench Protection System, Cryogenics System, Uninterruptible Power Supply and the ‘Arrêt d’Urgence Général’. The interface to this equipment is doubled (in series) via a CPU system (slow) and a matrix system (fast).

 

System tests without beam: Tests are to take place per IR and not per sector. For each IR two sectors are involved. One PIC interfaces to different cryogenics systems, which can be a practical problem during the hardware commissioning period. The test conditions required during the hardware commissioning / cold checkout period are listed on slide 8, and the testing of the different underlying systems are briefly summarise in the following slides. The circuit-by-circuit tests presented on slide 10 will be performed from the CCC. Tests also take place on the BIC level, including the redundancy of the dump request. Because these tests will need to be done with the machine cold, they will likely have to take place (as well) during the cold checkout period and will need to be automated to be done ‘fast’.

 

The delays between the beam dump request from the underlying equipment and the beam dump request issued by the BIS is important and should be measured (parasitically via the post mortem?). This can be done without beam.

 

There are no tests required with beam.

 

A draft version of the PIC MPS commissioning procedures has been put on the Web page page with procedures.

3. Status of the procedures and documentation of the other main systems

BIS system: Bruno gave a paper copy of the procedures to Jan, to be checked on some ‘basic assumptions’ (details of test should go to the clients!). He will make a presentation in the next meeting in 3 weeks.

 

BLM system: Work on the procedures has started, based on the HC documentation, but cold checkout and tests with beams to be added. Also to be presented in 3 weeks.

 

Collimator system: Ongoing.

 

Beam Dumping System: Ongoing – details of the different phases to be agreed upon.

 

Injection System: Should have something ready when the SPS is running again (beginning of June).

 

FMCM: Draft procedure received after the meeting, put on the Web page page with procedures.

 

WIC system: ongoing.

 

 

Jan Uythoven, 26/04/07.